A number of the City's Capital Projects are making progress toward completion.
NE 15th Avenue/NE 24th Street
Project implementation began in July 2022, with sidewalk improvements on NE 24th Street, followed by the implementation of the raised intersection on NE 15th Avenue. The NE 24th Street sidewalk improvements have been completed, and intersection improvements at NE 24th Street and NE 15th Street are almost completed. Intersection improvements at NE 22nd Street will begin once those are completed. Please see below for the NE 15th Avenue/NE 24th Street Construction Schedule.
NW 29th Street and NW 30th Court
New water main and service line replacements will be installed along NW 29th Street and sections of NW 30th Court. Both projects are in the engineering design phase with construction planned for the first quarter of 2023. These projects are included in the City’s Water, Wastewater & Stormwater Integrated Master Plan of infrastructure improvements to be implemented during the 10-year period 2021-2030, and will be partially funded through the American Rescue Plan Act (ARPA).
Lift Station Improvements
Lift Station 10
The CIPP lining was completed and service lateral grouting has begun.
Lift Station 11
30% progress plans were received on August 25, 2022.
Water Line Replacement
The City Commission approved Resolution 2022-094 during the October 11, 2022, City Commission meeting, approving a construction agreement with Murphy Pipeline Contractors to replace sewer lines in Manor Grove Condominiums.
Wilton Drive
The City contracted with Green Construction Technologies (GCT) to repair and improve the irrigation system on Wilton Drive, prior to the installation of landscaping. The upgrade of the irrigation system and the installation of about 60 trees were completed in September 2022. The Wilton Drive and Landscaping Irrigation project is now 95% complete. Permitting review is in progress for the installation of electrical receptacles along Wilton Drive.
Click here for more information on the City's capital projects.